SUBIC BAY FREEPORT — The Kalaklan Lighthouse Bridge, which connects the Subic Bay Freeport to Olongapo City and the rest of Zambales, will remain open until June 2010 while a new bridge is being constructed to replace it.
Subic Bay Metropolitan Authority Administrator Armand Arreza said the bridge will not be closed as originally planned, but will continue to be open to light vehicles and pedestrians in response to appeals made by the city government and business groups in Olongapo City.

Arreza has directed the agency’s Engineering Department to ask the project contractor to install additional safety mechanisms and regularly conduct maintenance work on the existing bridge to ensure public safety.

“We do not mind spending more for this project if it means ensuring that public interest is served adequately,” Arreza said.

SBMA’s move is expected to avert a potential traffic disaster in Olongapo, which would absorb all vehicular traffic from the Freeport to Zambales and vice versa once the existing bridge is closed.
SBMA engineers said an average of 2,500 light vehicles and some 300 pedestrians, mostly workers, pass through the Kalaklan Lighthouse Bridge daily.

The bridge construction project is part of the agency’s efforts to prepare for the eventual expansion of the Subic Bay Freeport into nearby areas like Olongapo.

SBMA Deputy Administrator for Public Works Engr. Mar Sanqui said the project contractor is also expected to submit a new program schedule, citing the possibility of a delay in the project completion, which was originally targeted for January next year.

The SBMA announced last month the start of construction work on the new bridge and the closure of the existing bridge to vehicular and pedestrian traffic starting February 15 and March 1, 2010, respectively.

Olongapo City officials and businessmen led by Mayor James Gordon Jr. have made representations with the SBMA to consider other options, citing the huge traffic volume that the city will have to take during the year-long construction period and the adverse impact on the tourism industry in Olongapo and Zambales during peak season in the summer months.
The Kalaklan Bridge, one of four bridges linking this free port to Olongapo City, will be replaced by a new two-lane concrete bridge with a covered walkway and a security plaza. It is also the Freeport’s gateway to Zambales.

Kalaklan Bridge and the Main Gate Bridge that leads to Magsaysay Drive, the city’s main business district, were built by the US Navy in the early ‘60s.

SBMA engineers noted last year that the bridges have been “structurally weakened”. The Main Gate Bridge has been closed to vehicular traffic while only pedestrians and light vehicles are allowed to pass through the Kalaklan Bridge. By FRANCO G. REGALA - Manila Bulletin

Labels: , , , ,

0 Comments:

Post a Comment

<< Home


 

This is a joint private blog of volunteers from Subic Bay. It is being maintained primarily to collate articles that may be of importance to decision making related to the future of Subic Bay and as a source of reference material to construct the history of Subic Bay.

The articles herein posted remains the sole property of original authors and publications which has full credits to the articles.

Disclaimer: Readers should conduct their own research and due diligence before using any article herein posted for whatever intended purpose it may be. This private web log will not be liable for any loss or damage caused by a reader's reliance on information obtained from volunteers of this private blog.

www.subicbay.ph, http://olongapo-subic.com, http://sangunian.com, http://olongapo-ph.com, http://oictv.com, http://brgy-ph.com, http://subicbay-news.com, http://batanggapo.com 16 January 2012