$500-m Masinloc Coal Plant expansion up

AES Corp. of the US has committed to expand the 600-megawatt Masinloc coal-fired power plant in Zambales province by an initial 300 MW at a cost of $500 million.

Andrew Horrocks, country manager of AES Philippines, told reporters at the sidelines of a conference Thursday that the company was waiting for government permits to go ahead with the expansion

“We are on expansion stage. We are going through the process, getting the environmental clearance certificate and final stage of permits,” Horrocks told reporters.

Horrocks expects to receive approval of the Masinloc permits by November. He said the coal plant expansion received strong support from the local communities.

“We have very good relationship with them, no problem with that,” he said.

Horrocks said the company hoped to start construction soon.

He said the company sought approval to expand the power plant by 600 MW.

“The first 300 MW [is] roughy around half a billion dollars. Our permitting is for 600 MW but our view is 300 MW by 2015,” the AES official said.

Labels: , , ,

Wednesday, October 01, 2008

Masinloc coal-fired plant posts US$ 36M income in the first six months of operations

US-based AES Philippines has posted about US$ 36 million income from the electricity sales of the 600 megawatt (MW) Masinloc coal-fired power plant in the first six month of its operations.

In its financial statement, AES Philippines, a subsidiary of AES Corp. reported that Masinloc power facility helped in boosting the revenues of its Asia’s slice during the period.

Based on the record, the Asia generation revenues went up to US$ 656 million from US$ 205 million as a result of higher rates driven by an increase in fuel prices at its facilities in Pakistan and an increase in rates at Kelanitissa in Sri Lanka.

AES Philippines acquired in July 2007 the Masinloc plant at US$ 930 million which they fully paid in April of this year.

AES official who requested not to be named said they are expecting their income to further increase with the release of the ruling of the Energy Regulatory Commission (ERC) on the pending petition for rate increase filed by state-run National Power Corporation (Napocor) recently.

The Masinloc plant's transition supply contracts with power distributors are linked to the rates of Napocor.

Seeing the potential of the Masinloc plant, AES president Matthew Bartley has committed to further infuse more investment in the country in particular Zambales. He said they are looking at spending another US$ 1 billion for the expansion of the power facility.

“As one of the world’s largest global power companies, our experience with the privatization of this plant reaffirms our interest in further investments in the Philippines particularly Zambales,” Bartley said in an earlier interview.

He also committed to immediately address the growing demand for electricity in the country by improving the capacity of the Masinloc plant to another 600 MW in the near future.

“In addition to maximizing the capability of the existing Masinloc generating facility, we shall immediately took to leverage other aspects of the existing project in providing the lowest cost, most reliable resource of incremental new capacity to Luzon. For Zambales and Masinloc, this would mean additional revenues for the further development of the province and the municipality and additional jobs for the Filipino people,” the AES president said.

But sources said AES may delay its plan expansion until the ERC released its ruling on the pending application rate increase of Napocor.

Located about 250 km northwest of Metro Manila, Masinloc plant covers a total of 137 hectares including 11 hectares on land reclaimed from the sea.

The power plant was designed and commissioned in 1998 as a two-unit, 600 MW plant. The plant utilizes refined coal from Australia, China, Indonesia and occasionally local coal. (PNA)

Labels: , , ,

Tuesday, May 06, 2008

Zambales gets P204 M from sale of power plant

In payment of sales and land-transfer taxes to provincial gov’t

MASINLOC, Zambales – As a result of the transfer of the 600-megawatt Masinloc coal-fired power plant to its new owner, the provincial government received more than P204 million in payment for sales and land-transfer taxes.


The acquisition of the Masinloc plant by AES Corp., a reputable, experienced independent power producer (IPP), was seen to enhance the competitive edge of the Philippine market for electricity generation.

It is expected that in the long run, this would help bring down electricity prices.

During a simple ceremony, Zambales Gov. Amor Deloso received from Masinloc Power Partners Co. Ltd. (MPPCL) President Mathew Bartley and MPPCL Chief Finance Officer Hassaan Mirza a symbolic check for R204,600,000 in payment of sales tax.

Deloso told reporters that the tax revenues derived from the sale of the Masinloc plant located in Barangay Bani here would be used to fund projects aimed at improving the delivery of social services and meeting much-needed infrastructure requirements of the province.

The facilities and operations of power plant was also formally turned over to AES Corp., one of the world’s largest global power companies.

Bartley said that AES has already paid the whole amount of $ 930 million to the Power Sector Assets and Liabilities Management (PSALM). The amount is in payment for the total winning bid price of the coal plant last month.

Deloso said that the provincial government is projecting a 30-centavo reduction in power rates per kilowatthour in the electric bills of household power consumers in the coming months. He described the revenue and other powerrate reduction as a windfall that will directly benefit his constituents.

AES is eyeing the upgrading of the plant’s capacity from 600 MW to 1200 MW in the next five years.

In a statement, AES President and Chief Executive Officer Paul Hanrahan said that the "acquisition is a key component of our strategy to invest in areas where there is a significant need for new capacity and offers AES an excellent entry point into the growing Philippine economy through the lowest cost thermal plant in the system."

"This is a particularly attractive investment because the existing facility has the infrastructure in place to allow AES to add 600 megawatts to our generation capacity," AES said.

Approximately 60 percent of the electricity generated at the Masinloc plant will be sold to electric distribution companies, cooperatives, and special economic zones through power-supply contracts of various terms.

The remaining capacity will be sold through the wholesale power pool or under new contracts.

The government hopes that the operation of the power plant will improve the investment climate by ensuring the reliability of the generating capacity for commercial and industrial uses. By FRED ROXAS - Manila Bulletin

Labels: , , ,

Thursday, April 24, 2008

Masinloc owners assure consumers of better services

ZAMBALES -- New owners of the 600-megawatt (mW) Masinloc coal-fired power facility said their consumers would have an efficient, reliable and cheap electricity rates.

Paul Hanrahan, president and chief executive office (CEO) of US-based AES Corporation, said they consider the acquisition of Masinloc an "excellent entry point" to the Philippine market since they had been wanting for a long time to have presence in the country.

"This is a particularly attractive investment because the existing facility has the infrastructure in place to allow AES to add an additional 600 MW of generation capacity. As AES has done through similar acquisitions in other parts of the world, we expect to improve the overall efficiency and output of the existing plant, providing more reliable energy to the Philippine market," Hanrahan said.

The 660-MW (gross) Masinloc coal-fired thermal power plant is located in Barangay Bula, Zambales.

Hanrahan said at least 60 percent of the electricity generated at the Masinloc plant will be sold to electric distribution companies, cooperatives and special economic zones via power supply contracts of various tenors in place at the plant turnover.

On the other hand, the remaining capacity will be sold through the wholesale power pool or under new contracts.

Last April 16, AES and its eight percent minority partner International Finance Corporation (IFC) fully settled the US$930 million purchase price.

The full payment includes transaction costs and completion of a planned upgrade program to improve environmental and operational performance, the total project cost is estimated at US$1.057 million.

According to Hanrahan, the transaction funding included US$635 million in secured non-recourse financing comprised of a US$240 million, 18-year facility from IFC; a US$200 million, 15-year facility from Asian Development Bank (ADB); and a US$195 million, 10-year facility from a consortium of banks including ING Bank, Security Bank, Bank of Philippine Islands (BPI) and Rizal Commercial Banking Corporation (RCBC).

In addition, over US$30 million of unsecured working capital facility commitments have been obtained from three local banks.

AES has been operating in Asia since 1994. Today, AES' businesses in the region include electric utilities and generation facilities in China, India, Jordan, Oman, Pakistan, Qatar and Sri Lanka. It has more than 5,000 MW of generation capacity in the region. (MSN/Sunnex)

Labels: , ,

Thursday, April 17, 2008

Masinloc plant paid in full

AES Corp. of the US yesterday paid $930 million in full to complete its acquisition of the 600-megawatt Masinloc coal-fired power plant in Zambales province and committed to expand operations in the Philippines.

Matthew Bartley, AES Philippines chief executive, told reporters at the sidelines of the turnover ceremonies that his company planned to increase its power generation portfolio in the Philippines by bidding for the other assets of National Power Corp.

“We offered a bid for Tiwi-Makban. We haven’t got geo and we’re very interested to add that to our portfolio,” Bartley said at the office of Power Sector Assets and Liabilities Management Corp.

PSALM will bid out the 747-MW Tiwi-MakBan geothermal power complex by June 4. It scheduled the second pre-bid conference by next week.

“We are looking at hydros as well. We want to have a balance of baseload and peaking plants,” the AES executive said.

AES and International Finance Corp., which holds an 8 percent stake, raised the $930-million financing for the plant. The funding included $635 million in secured non-recourse financing comprising of a $240-million 18-year facility from IFC, a $200-million, 15-year facility from the Asian Development Bank and a $195-million, 10-year facility from a consortium of banks, including ING Bank, Security Bank, Bank of the Philippine Islands and Rizal Commercial Banking Corp.

The three local banks also provided unsecured working capital facilities worth $35 million.

Bartley assured that AES would start securing permits that will pave the way for the expansion of the Masinloc facility by an additional 600 MW.

He reiterated that the company would infuse an additional $1 billion to expand the plant’s capacity and another $45 million to upgrade and make it more efficient.

“The impressive local and international group of commercial and multilateral lenders reflects not only the strong fundamentals of the project but also demonstrates the strength of the project finance market in Asia,” Mark Woodruff, AES executive vice president, said.

PSALM president Jose Ibazeta said proceeds of the payment would go to the liquidation of Napocor’s debts, as specified in the Electric Power Industry Reform Act of 2001.

Ibazeta said the $930 million was part of PSALM’s total target privatization proceed of $1.9 billion this year. Last year, PSALM raised about $500 million from the privatization of Napocor’s plants.

“This is a particularly attractive investment because the existing facility has the infrastructure in place to allow AES to add an additional 600 MW of generation capacity. As AES has done similar acquisitions in the other parts of the world, we expect to improve overall efficiency and output of the existing plant, providing more reliable energy to the Philippine market,” AES president and chief executive Paul Hanrahan said. By Alena Mae S. Flores - Manila Standard Today

Labels: , , ,

Friday, February 08, 2008

AES paying $930-m Masinloc bid in full next week

By Alena Mae S. Flores - Manila Standard Today

AES Corp. of the US is expected to pay its entire $930-million bid for the 600-megawatt Masinloc coal plant facility in Zambales anytime next week, a government official said yesterday.
Jose Ibazeta, president of Power Sector Assets and Liabilities Management Corp., told reporters that AES officials had indicated the company would pay the full amount on or before Feb. 15.

AES is required to make a 40 percent down payment and pay the 60 percent balance over a certain number of years.

Ibazeta said the company was opting for a full payment, instead, to take advantage of lower interest rate on borrowings.

“We’re just waiting for something to be completed from our side. There are some issues we have yet to complete. Like the land, right of way issues, etc,” Ibazeta said.

AES has been working on the financing package to pay for the acquisition of the Masinloc coal facility.

AES received a financing package from International Finance Corp., the investment arm of the World Bank, of up to $275 million to partly fund the acquisition. A portion of the IFC financing package will be invested in the power plant as equity.

The Asian Development Bank has offered the same amount to AES, which also initiated talks with some local banks to fund the acquisition.

The purchase of the Masinloc facility is estimated to cost approximately $1.1 billion, which includes the acquisition price, funding for the debt service reserve account, transaction costs refurbishment works and initial working capital needs.

AES is looking at additional investments of another $1 billion to expand the capacity of the Zambales plant by another 600 MW.

“We are intending to expand and double Masinloc’s capacity as soon as we complete the acquisition. We may spend up to another $1 billion,” Matthew Bartley, AES Philippines president and chief executive, told reporters earlier.

Labels: , ,

Tuesday, November 20, 2007

$1-b Masinloc expansion

AES Philippines, the winning bidder of the 600-megawatt Masinloc coal plant facility, is looking at investing another $1 billion to expand the capacity of the Zambales plant by another 600 MW, a company official said.

“We are intending to expand and double Masinloc’s capacity as soon as we complete the acquisition. We may spend up to another $1 billion,” Matthew Bartley, AES Philippines president and chief executive, told reporters.

Bartley said AES, one of the US’ biggest power industry players, was looking at a “greenfield” or an entirely new power project to meet the growing electricity demand in the Philippines.

He said AES might also participate in the bidding of the generation assets of National Power Corp. set to be auctioned by the Power Sector Assets and Liabilities Management Corp.

“We are a global company. We invest in whatever makes business sense. We may look at some hydro assets,” Bartley said.

Bartley said the company was focusing on closing the Masinloc plant acquisition. AES won the bidding with a bid of $930 million.

“We are hoping to get all the approvals [from PSALM] on the closing then start construction [of the expansion],” he said.

Bartley said the company hoped to close the transaction in the first quarter of 2008 or earlier.

AES is expected to come up with the 40 percent upfront payment as a pre-condition to the closing of the sale transaction.

Bartley said the company was working with several lending institutions, including International Finance Corp., to partly fund the acquisition.

“We are talking with international lenders, including IFC and several other multilaterals,” the AES official said.

IFC has expressed interest to provide up to $275 million to AES, including a possible equity investment.

AES is also working out a similar financing arrangement with the Development Bank of the Philippines.

The total acquisition cost of the Masinloc facility is estimated at approximately $1.1 billion, including funding for the debt service reserve account, transaction costs, refurbishment works and initial working capital needs.

The Masinloc plant is located about 250 kilometers northwest of Metro Manila, covering about 137 hectares, including 11 hectares of reclaimed land.

The power plant was designed and commissioned in 1998 as a two-unit, 600-MW plant. The plant utilizes refined coal from Australia, China, Indonesia and occasionally local coal.

AES is a leading global power developer and operator in the world. It is listed on the New York Stock Exchange. The company has 13 regulated utilities and 121 generation facilities, with total generation capacity of around 43,000 MW.
By Alena Mae S. Flores - Manila Standard Today

Labels: , ,


 

This is a joint private blog of volunteers from Subic Bay. It is being maintained primarily to collate articles that may be of importance to decision making related to the future of Subic Bay and as a source of reference material to construct the history of Subic Bay.

The articles herein posted remains the sole property of original authors and publications which has full credits to the articles.

Disclaimer: Readers should conduct their own research and due diligence before using any article herein posted for whatever intended purpose it may be. This private web log will not be liable for any loss or damage caused by a reader's reliance on information obtained from volunteers of this private blog.

www.subicbay.ph, http://olongapo-subic.com, http://sangunian.com, http://olongapo-ph.com, http://oictv.com, http://brgy-ph.com, http://subicbay-news.com, http://batanggapo.com 16 January 2012